Overview

The City will analyze and redesign the intersection of Parkway Avenue and Main Street.  The redesign will include updating the current signal, intersection layout, ADA ramps, and crosswalks to improve safety while providing more efficient traffic flow and improved pedestrian accessibility.

Funding

The City continues to pursue funding opportunities for the construction portion of this project.  

Preliminary Engineering$100,000$100,000
Right of Way$25,000$25,000
ConstructionTBDTBD
PROJECT TOTAL
$125,000*
$125,000*

*Preliminary Project Total - Pending construction cost totals.  Construction estimates will be determined at the conclusion of the preliminary engineering/design phase of the project. 

City FundsPhase Total


Project Timeline

The Preliminary Engineering the Right-of-Way phases of this project are running concurrently. 

Preliminary Engineering2024 - 1st Quarter2025 - 4th Quarter
Right of Way2026 - 1st Quarter​2026 - 1st Quarter
Construction2026 - 2nd Quarter2026 - 3rd Quarter

*Yellow indicates current project phase


Project Location

Click to enlarge

Parkway and Main Location Map