The project will incorporate a compact roundabout to improve pedestrian safety at intersection of NW 20th Avenue and NW 9th Street.  The project will incorporate improved street lighting, ADA ramp replacement, rectangular rapid flashing beacons, and crosswalk improvements.  The compact roundabout is designed to fit in the footprint of the existing intersection.

Funding

Preliminary Engineering (PE)$61,800$116,500$178,300
Right-of-Way (ROW)$0$86,600$86,600
Construction (CN)$0$548,700$548,700
PROJECT TOTAL$0$787,800$813,600


City Funds*Federal FundsPhase Total

*The project has Federal funding through the Highway Safety Improvement Program.

Project Timeline

Preliminary Engineering (PE)2023 - 2nd Quarter​2026 - 3rd Quarter​
Right-of-Way (ROW) 2026 - 2nd Quarter2026 -3rd Quarter
Construction (CN)2026 - 4th Quarter2027 - 2nd Quarter

*Yellow indicates current project phase.

Project Location

NW 9th St  and NW 20th Ave Intersection Improvements

Conceptual Drawing