SE Grace Avenue - Phase II

Overview

Reconstruction of SE Grace Avenue, between East Main Street and SE Rasmussen Boulevard, includes aligning the section of roadway with NE Grace Avenue at East Main Street and signalizing the new intersection. 

The new road will have a through lane in each direction, a center turn lane, bike lanes, planter strips and sidewalks.  

Funding

Preliminary Engineering$330,000XX$330,000
Right of Way$600,000$500,000$400,000$1.5M
Construction$600,000$2.5M$3.9M$7M
PROJECT TOTAL$1.53M$3M$4.3M$8.8M


City Funds*State Funds**Federal FundsPhase Total

*State Funds are provided through the Transportation Improvement Board.
**Federal Funds are provided through a Surface Transportation Block Grant, which was awarded by the Regional Transportation Commission. 

Project Timeline

Preliminary Engineering (PE)2017 - 1st Quarter2026
Right-of-Way (ROW)2024 - 3rd Quarter ​2027 (estimate)
Construction (CN)2027 - 2nd QuarterTBD

The engineering design for the project is approximately 60% complete.  Federal environmental review has been completed.  The project is currently in the Right-of-Way phase which is expected to be completed in 2027.  

Existing SE Grace Avenue (looking south)

Grace Avenue Phase II - Project Location

SE Grace Avenue Phase II - Project Location

Map - Grace